 Mark J. Kaiser.A Review of Deepwater Pipeline Construction in the U. S. Gulf of Mexico-Contracts, Cost, and Installation Methods[J].Journal of Marine Science and Application,2016,(3):288-306.[doi:10.1007/s11804-016-1373-7]
Click and Copy

A Review of Deepwater Pipeline Construction in the U. S. Gulf of Mexico-Contracts, Cost, and Installation Methods

Info

Title:
A Review of Deepwater Pipeline Construction in the U. S. Gulf of Mexico-Contracts, Cost, and Installation Methods
Author(s):
Mark J. Kaiser
Affilations:
Author(s):
Mark J. Kaiser
Center for Energy Studies, Louisiana State University, Baton Rouge70803, USA
Keywords:
construction costcontract typeempirical statisticsinstallation methodsdeepwater pipelinereview
分类号:
-
DOI:
10.1007/s11804-016-1373-7
Abstract:
The offshore pipeline network in the U.S. Gulf of Mexico is the largest and most transparent system in the world. A review of deepwater projects in the region provides insight into construction cost and installation methods and the evolution of contract strategies. Pipeline projects are identified as export systems, infield flowline systems, and combined export and infield systems, and three dozen deepwater pipeline installations from 1980-2014 are described based on Offshore Technology Conference (OTC) and Society of Petroleum Engineers (SPE) industry publications and press release data. Export lines and infield flowlines are equally represented and many projects used a combination of J-lay, S-lay and reel methods with rigid steel, flexible line, and pipe-in-pipe systems. The average 2014 inflation-adjusted cost for pipeline projects based on OTC/SPE publications was $2.76 million/mi and ranged from $520 000/mi to $12.94 million/mi. High cost pipelines tend to be short segments or specialized pipeline. Excluding the two cost endpoints, the majority of projects ranged from $1 to $6million/mi. The average inflation-adjusted cost to install deepwater pipelines in the U.S. Gulf of Mexico based on available public data is estimated at $3.1 million/mi.

References:

Al Sharif M, 2007. Independence trail-pipeline design. Offshore Technology Conference, Houston, OTC 19056.
Arthur TT, Cook EL, Chow JK, 1994. Installation of the Mobile Bay offshore pipeline systems. Offshore Technology Conference, Houston, OTC 7572.
Bai Y, Bai Q, 2012. Subsea engineering handbook. Gulf Professional Publishing, Houston, Texas.
Ballard AL, 2006. Flow-assurance lessons: The Mica tieback. Offshore Technology Conference, Houston, OTC 18384.
Beckmann MM, Riley JW, Volkert BC, Chappell JF, 1998. Troika- towed bundle flowlines.Offshore Technology Conference, Houston, OTC 8848.
Berger RK, McMullen ND, 2001. Lessons learned from Troika andflow assurance challenges. Offshore Technology Conference, Houston, OTC 13074.
Boening DE, Howell ER, 1984. Lena guyed tower project overview. Offshore Technology Conference, Houston, OTC 4649.
Bourgeois TM, 1994. Auger tension leg platform: Conquering the deepwater Gulf of Mexico. International Petroleum Conference of Mexico, Veracruz,SPE 28680.
Burman J, Kelly GF, Renfro K,Shipper DW, 2007. Anadarko Independence project completion campaign: Executing the plan. SPE Annual Technical Conference and Exhibition, Anaheim, SPE 110110.
Clarke DG, Cordner JP, 1996. BP exploration’s Pompano subsea development: Operational strategy for a subsea project. Offshore Technology Conference, Houston, OTC 8209.
Cooke JC, Cain RE, 1992. Development of conventionally uneconomic reserves using subsea completion technology: Garden Banks block 224, Gulf of Mexico. Offshore Technology Conference, Houston, OTC 7004.
Cooley C, Wallace BK, Guimetla R, 2003. Hydrate prevention and methanol distribution on Canyon Express. SPE Annual Technical Conference and Exhibition, Denver, SPE 84350.
DeReals TB, Nogueira AC, Ferroni LB, 2003. Canyon Express flowline system: Design and installation. Offshore Technology Conference, Houston, OTC 15096.
Digre KA, Brasted LK, Marshall PW, 1989. The design of the Bullwinkle platform. Offshore Technology Conference, Houston, OTC 6050.
Gallagher MJ, Arthur TT, Boening DE, Sortland KA, 1994. An overview of the Mobile Bay project offshore facilities and installation approach. Offshore Technology Conference, Houston, OTC 7448.
Gerwick B, 2007.Construction of marine offshore structures. 3rd Ed. CRC Press, Boca Raton.
Gillespie G, Angel KF, Cameron JA, Mullen ME, 2005. Troika field: A well failure, and then a successful workover.SPE Annual Technical Conference and Exhibition, Dallas, SPE 97291.
Godfrey DG, Haney JP, Pippin AE, Stuart CR, Johnston DD, Oriean RH, 1997. The Mars project overview. Offshore Technology Conference, Houston, OTC 8368.
Grant L, Japar NJ, Van Den Haak A, 2014.The use of a “type well” concept approach for design, feasibility, and creation of a technology plan for well construction in a new Gulf of Mexico deepwater development.SPE Annual Technical Conference, Amsterdam, SPE 170791.
Haney JP, Johnston DD, Stuart CR, Rodrigue MJ, FerrariS, Meek J, Smith FA, 1997. Mars project alternative contracting approach. Offshore Technology Conference, Houston, OTC 8370.
Holley SM, Abendschein RD, 2007.Independence project overview-A producer’s perspective.Offshore Technology Conference, Houston, OTC 18721.
Hoose JW, Schneider DR, Cook EL, 1996. Rocky flowline project-The Gulf of Mexico &first reeled pipe-in-pipe. Offshore Technology Conference, Houston, OTC 8131.
Hudson JD, Dutsch DB, Lang PP, Lorimer SL, Stevens KA, 2002. An overview of the Na Kika flow assurance design. Offshore Technology Conference, Houston, OTC 14186.
Johnson HE, Kartzke RJ, Kruger RM, 1994. The Mobile Bay project. Offshore Technology Conference, Houston, OTC 7447.
Kennefick J, Lang P, Hervey D, 1999. Morpeth export system. Offshore Technology Conference, Houston, OTC 10859.
Kleinhans JW, Cordner JP, 1997. Pompano through-flowline system. SPE Annual Technical Conference, San Antonio, SPE 38771.
Koon JR, Langewis C, 1990. Jolliet: The project. Offshore Technology Conference, Houston, OTC 6359.
Koon JR, Heijermans B, Wybro PG, 2002. Development of the Prince field. Offshore Technology Conference, Houston, OTC 14173.
Kopp F, Barry DW, 1994. Design and installation of Auger pipelines. Offshore Technology Conference, Houston, OTC 7619.
Kopp F, Light BD, Preli TA, Rao VS, Stingl KH, 2004.Design and installation of the Na Kika export pipelines, flowlines and risers. Offshore Technology Conference, Houston, OTC 16703.
Lamey MF, Schoppa W, Stingl KH, Turley AJ, 1999. Dynamic simulation of the Europa and Mars expansion projects: A new approach to coupled subsea and topsides modeling. SPE Annual Technical Conference, Houston, SPE 56704.
Langner CG, Wilkinson HM, 1980. Installation of the Cognac 12-inch pipeline.Offshore Technology Conference, Houston, OTC 3740.
Marshall R, McDonald W, 2004. Mardi Gras transportation system overview. Offshore Technology Conference, Houston, OTC 16637.
Maus LD, Finn LD, Turner JW, 1985. Development of the guyed tower: A case history. Journal of Petroleum Technology, 37(4), 651-659.
Meng W, Ogea P, King M, 2011. Changes of operating procedures and chemical application of a mature deepwater tie-back-Aspen field case study. Offshore Technology Conference, Houston, OTC 21402.
Nations JF, Speice CB, 1982. The field development of Cognac (Mississippi Canyon 194) field: A case history. SPE Fall Technical Conference, New Orleans, SPE 10955.
Palmer AC, King RA, 2008. Subsea pipeline engineering. Penn Well, Tulsa.
Rijkens F, Allen M, Hassold T, 2003. Overview of the Canyon Express project, business challenges and “industry firsts.” Offshore Technology Conference, Houston, OTC 15093.
Roach WJF, Knight VC, Lochte GE, Kibbee SE, Mackintosh N, 1999.Morpeth field development overview. Offshore Technology Conference, Houston, OTC 10854.
Schneider DR, 2001. A history of a Gulf of Mexico deepwater subsea production system development strategy. Offshore Technology Conference, Houston, OTC 13116.
Simon JV, Edel JC, Melancon C, 1999. An overview of the Baldpate project. Offshore Technology Conference, Houston, OTC 10914
Smetak EC, Lombardi J, Roussel HJ, Wozniak TC, 1984. Jacket, deck, and pipeline installation-Lena guyed tower. Offshore Technology Conference, Houston, OTC 4683.
Sterling GH, Krebs JE, Dunn FP, 1989. The Bullwinkle project: An overview. Offshore Technology Conference, Houston, OTC 6049.
Tillinghast WS, 1990. The deepwater pipeline system on the Jolliet project.Offshore Technology Conference, Houston, OTC 6403.
Vercher CM, Blakeley D, 2007. Codevelopment of Spiderman and San Jacinto fields. Offshore Technology Conference, Houston, OTC 18590.
Willson SM, Edwards S, Heppard PD, LiX, Coltrin G, Chester DK, Harrison HL, Cocales BW, 2003. Wellbore stability challenges in the deep water, Gulf of Mexico: Case history examples from the Pompano field. SPE Annual Technical Conference and Exhibition, Denver, SPE 84266.

Memo

Memo:
Received date: 2016-1-23;Accepted date: 2016-4-1。
Corresponding author: Mark J. Kaiser,E-mail:mkaiser@lsu.edu
Last Update: 2016-09-02